Method of application insulated concrete system for the installations according to the standard specifications 0421
1- It is preferable for the main contractor to be fully aware of all specifications and details related to this section of the business, in order to ensure the quality of work and full compliance and adherence to all the conditions listed below.
General Conditions:
The procedures required to be followed by the main contractor before and after performing the concrete insulation works using crystal materials (CA112 / CA113) to be mixed with the concrete:
1- The material CA112 / CA113 as a powder in 25 kg bag.
2- The material must be mixed with water before adding to concrete, based on the ratio (1 kg of the substance to 1.25 water.)
3- The ratio that should be follow (4 kg of the substance with 5 liters of water) to every cubic meter of concrete.
4- The material must be added at the site of implementation.
5- The final mixture must be mixed in the mixing car for a sufficient period of not less than 5 minutes.
6- The site official must carried out concrete tests.
7- Vibrators should be secured in sufficient number to ensure homogeneity of concrete and that nesting does not occur.
8- Adhering to the above-mentioned action steps, the facility will avoid later maintenance work.
• In case that the above mentioned steps are adhered to, the warranty period against leakage is 25 years
General Conditions:
The procedures required to be followed by the main contractor before and after performing the concrete insulation works using crystal materials (CA112 / CA113) to be mixed with the concrete:
1- The material CA112 / CA113 as a powder in 25 kg bag.
2- The material must be mixed with water before adding to concrete, based on the ratio (1 kg of the substance to 1.25 water.)
3- The ratio that should be follow (4 kg of the substance with 5 liters of water) to every cubic meter of concrete.
4- The material must be added at the site of implementation.
5- The final mixture must be mixed in the mixing car for a sufficient period of not less than 5 minutes.
6- The site official must carried out concrete tests.
7- Vibrators should be secured in sufficient number to ensure homogeneity of concrete and that nesting does not occur.
8- Adhering to the above-mentioned action steps, the facility will avoid later maintenance work.
• In case that the above mentioned steps are adhered to, the warranty period against leakage is 25 years
Views
- 3104 Total Views
- 2476 Website Views
- 628 Embeded Views
Actions
- Social Shares
- 3
- 0
- 0 Comments
Share count
- 0 Facebook
- 0 Twitter
- 0 LinkedIn
Embeds 3
- 46 www.sab-us.com
- 2 161.97.92.48:8011
- 6 161.97.92.48
-
LAVATEX 2000
10025 Views . -
DCL Product Conformity
5517 Views . -
Optimization Methodology To Implement Thermal
5306 Views . -
الوقاية من الحرارة والرطوبة العزل المائي
5257 Views . -
طبقات نظام العزل كومبو رووف
4937 Views . -
VELOSIT® TDS-PC-221-EN_2319 (Plug Cement)
4785 Views . -
Wurth sealants & Adhesives
4691 Views . -
AWAZEL PU 250 White
4536 Views . -
Fosroc Conbextra EPGP
4239 Views . -
Approved Materials (TDS) for Sabtron Combo System
4211 Views . -
Dr. Fixit PVA BOND.
4004 Views . -
SAB Trade Mark Certificate
3946 Views .