Method of application insulated concrete system for the installations according to the standard specifications 0421
1- It is preferable for the main contractor to be fully aware of all specifications and details related to this section of the business, in order to ensure the quality of work and full compliance and adherence to all the conditions listed below.
General Conditions:
The procedures required to be followed by the main contractor before and after performing the concrete insulation works using crystal materials (CA112 / CA113) to be mixed with the concrete:
1- The material CA112 / CA113 as a powder in 25 kg bag.
2- The material must be mixed with water before adding to concrete, based on the ratio (1 kg of the substance to 1.25 water.)
3- The ratio that should be follow (4 kg of the substance with 5 liters of water) to every cubic meter of concrete.
4- The material must be added at the site of implementation.
5- The final mixture must be mixed in the mixing car for a sufficient period of not less than 5 minutes.
6- The site official must carried out concrete tests.
7- Vibrators should be secured in sufficient number to ensure homogeneity of concrete and that nesting does not occur.
8- Adhering to the above-mentioned action steps, the facility will avoid later maintenance work.
• In case that the above mentioned steps are adhered to, the warranty period against leakage is 25 years
General Conditions:
The procedures required to be followed by the main contractor before and after performing the concrete insulation works using crystal materials (CA112 / CA113) to be mixed with the concrete:
1- The material CA112 / CA113 as a powder in 25 kg bag.
2- The material must be mixed with water before adding to concrete, based on the ratio (1 kg of the substance to 1.25 water.)
3- The ratio that should be follow (4 kg of the substance with 5 liters of water) to every cubic meter of concrete.
4- The material must be added at the site of implementation.
5- The final mixture must be mixed in the mixing car for a sufficient period of not less than 5 minutes.
6- The site official must carried out concrete tests.
7- Vibrators should be secured in sufficient number to ensure homogeneity of concrete and that nesting does not occur.
8- Adhering to the above-mentioned action steps, the facility will avoid later maintenance work.
• In case that the above mentioned steps are adhered to, the warranty period against leakage is 25 years
Views
- 4062 Total Views
- 3171 Website Views
- 891 Embeded Views
Actions
- Social Shares
- 3
- 0
- 0 Comments
Share count
- 0 Facebook
- 0 Twitter
- 0 LinkedIn
Embeds 5
- 52 www.sab-us.com
- 5 161.97.92.48:8011
- 16 161.97.92.48
- 154 www.google.com
- 8
-
LAVATEX 2000
12172 Views . -
الوقاية من الحرارة والرطوبة العزل المائي
7381 Views . -
DCL Product Conformity
7115 Views . -
Optimization Methodology To Implement Thermal
6542 Views . -
Wurth sealants & Adhesives
6445 Views . -
VELOSIT® TDS-PC-221-EN_2319 (Plug Cement)
5981 Views . -
AWAZEL PU 250 White
5952 Views . -
طبقات نظام العزل كومبو رووف
5874 Views . -
Approved Materials (TDS) for Sabtron Combo System
5401 Views . -
Fosroc Conbextra EPGP
5270 Views . -
Dr. Fixit PVA BOND.
5106 Views . -
صقل و تنعيم الخرسانة Power floating conc
4932 Views .